Draft Nottinghamshire Minerals Local Plan
Representation ID: 30892
Received: 20/09/2018
Respondent: Cemex UK operations
CEMEX strongly object to the provision of aggregate set out in Policy MP1 as the figure of 32 million tonnes arrived at by taking a 10 average of sales does take account of future demand going forward. It appears to CEMEX therefore that the plan seriously underprovides for needs of the economy which will as a consequence result into potentially unsustainable imports into the county.
In addition, it is noted that the policy makes provision for the maintenance of a landbank of 7 years yet the provision is just for the plan period.
CEMEX strongly object to the provision of aggregate set out in Policy MP1 as the figure of 32 million tonnes arrived at by taking a 10 average of sales does take account of future demand going forward. It appears to CEMEX therefore that the plan seriously underprovides for needs of the economy which will as a consequence result into potentially unsustainable imports into the county.
In addition, it is noted that the policy makes provision for the maintenance of a landbank of 7 years yet the provision is just for the plan period.