Draft Site Selection Methodology
5. Stage 3: Site assessment
Categorising sites
5.4 Once categorised by mineral type, the following categories are proposed to be applied:
- Permitted sites
- Extension to existing site
- Greenfield/ new site
- Sustainable transport available (river, rail or pipeline)
- Scale of extraction based on reserves available
- Small: Less than 500,000 tonnes
- Medium: Between 500,000 tonnes and 3 million tonnes
- Large: Over 3 million tonnes
- Lead in time to extraction
- Beginning of Plan period – 2029 – 2034
- Middle of Plan period – 2034 – 2039
- End of Plan period – 2039 – 2045
- Beyond Plan period – Beyond 2045
Question 2: Do you agree with the proposed categories? Are there any others we should consider at this stage? Comment
Initial sift
- The South Muskham Archaeological Resource Area
- Potentially the Holbeck/ Creswell Archaeological Resource Area, depending on feedback gained from the scoping consultation
- Site of Special Scientific Interest, National Nature Reserve or Special Area of Nature Conservation
- The possible potential Special Protection Area (ppSPA) for Sherwood Forest. This is a site of European importance which is being considered for such designation by Natural England.
Detailed assessment
- The operator/ proposer for the site
- Overall assessment work for sites, including:
- SEA
- Strategic Flood Risk Assessment
- Transport Assessment
- Habitats Regulation Assessment
- Landscape Impact and Visual Assessment
Assessment of suitability
Biodiversity and nature conservation
Designated ecological sites, including:
- Special Protection Areas (SPA)
- Special Areas of Conservation (SAC)
- National Nature Reserves (NNR)
- Site of Special Scientific Interest (SSSI)
- Local Wildlife Sites (LWS)
- Local Nature Reserves (LNR)
- Local Geological Sites (LGS)
- Green Space Sites
- Ancient Woodland
The ppSPA at Sherwood Forest, which is not currently designated.
Areas identified in the Local Nature Recovery Strategy, including:
- Scheduled Ancient Monuments (SAM)
- Listed buildings and their settings
- Conservation areas
- Registered parks, gardens and battlefields
- Other designated and non-designated heritage assets shown in the Nottinghamshire Historic Environment Record
- The South Muskham archaeological resource area
- Potentially the Holbeck/ Cresswell archaeological resource area
Question 3: Do you agree with the identified constraints that should be used to assess sites listed above? Are there any constraints we are missing? Comment
Table 1: RAG grading system for assessment of suitability
5.15Issues that will be considered include:
- Lead in times for planning permission to be obtained
- Land ownership
- Securing appropriate mineral rights
- Production rates
Table 2: RAG grading system for assessment of availability
| Grade | Description |
| Red |
Site is not available for mineral development during the Plan period due to issues identified |
| Amber | |
| Green |
Table 3: RAG grading system for assessment of achievability
| Grade | Description |
| Red | |
| Amber | |
| Green |
Mineral development at the site has shown or can show that extraction is achievable and viable |
Table 4: Final RAG grading system for detailed assessment
| Grade | Description |
| Red |
Due to constraints and assessment findings, the site is not currently a candidate for allocation |
| Amber | |
| Green |
Question 4: Do you have any comments on the detailed assessment, including the proposed assessment, including the proposed RAG grading system? Comment